Moon Festival, Golden Week and Chinese New Year: Why a January Order Cannot Land in February
China's factories pause for the Moon Festival, stop for Golden Week and close for weeks around Chinese New Year. What that does to an imported order, the dates we are working to, and why our Markham stock and Canadian-made lines are the calm way through the winter.
Every autumn a client calls with a February event, a product they love, and a quote that looks perfectly reasonable. We look at the calendar and have to say the thing nobody wants to hear: that item is made in China, and there is no version of this order that arrives in February. This is the post we wish we could hand them in September.
Three holidays, one long winter
China’s factory year has a rhythm that does not show up on a product page. It slows in late September, stops in early October, and then, a few months later, stops properly for the better part of a month. Knowing where those pauses fall is most of the battle.
The Moon Festival: September 25 to 27, 2026
Mid-Autumn is a family holiday, mooncakes and a full moon, and on its own it costs our suppliers a day or two. What matters this year is timing. It lands four days before the National Day break, so a lot of factories simply coast from the 25th of September to the 8th of October. If you are waiting on a proof that week, be patient with it.
Golden Week: October 1 to 7, 2026
The National Day holiday is a week on paper and closer to ten days in practice. The last week of September is the scramble to get everything finished and on a truck before the gates close. Couriers are swamped, air cargo gets expensive, and once October arrives nothing leaves the building until roughly the 8th. If an order of yours is mid-production on October 1, it will come out the other side about two weeks later than it otherwise would have.
Chinese New Year: February 6, 2027
This is the one that reshapes the whole first quarter. The public holiday is a week. The reality is that the workforce goes home to villages hundreds of kilometres away, and the factories close about ten days before New Year and reopen about eight days after. Mark it down: January 27 to February 14, 2027. Then add the part the calendar does not show. Workers drift back over two or three weeks. Some do not come back at all. Machines restart on the jobs that were already waiting, not on the ones that arrived by email during the break. A factory is not back to normal until late February or early March.
The honest version: for a custom item made in China, there is a gap from late January to about the third week of March where a new order cannot be delivered. Orders confirmed before the middle of December arrive before the gap. Orders placed in January arrive after it.
Why this is a smaller problem at Delite than it sounds
We have been importing from China since 1997, and we have spent most of those years building the alternative to waiting. Our warehouse in Markham, Ontario holds more than 300 products in stock, decorated in-house, with live inventory counts on every product page. A stocked item does not care what day it is in Guangdong. A foldable cotton mesh bag, a bamboo cutting board, a stone paper notebook or a double-duty flask can be engraved, printed and on a UPS truck in the same week in February that our overseas suppliers are still counting who came back to work.
Then there is the Canadian-made shelf. Black walnut boards cut in Canada, maple syrup in a leaf bottle, soap made without plastic. None of it has ever seen a container ship. For a February or March gift program, Canadian-made is not just a nice story on the card. It is the only category with a lead time we fully control that month.
Three questions to ask before you promise a date
- Where is it made, and is it on our shelf? The product page tells you. “In stock” with a count means Markham. No count means it is coming from overseas and the holiday calendar applies.
- Does production cross a closure? Take the production days on the page, add a week to ten days for air freight and customs, and lay it over the dates above. If any part of that span touches October 1 to 8 or January 27 to February 14, move the order earlier or move the product.
- Has the artwork been approved? Nothing starts until it has. A proof that waits a week in mid-December can push an order from “before the shutdown” to “after it” with nobody doing anything wrong.
The dates we are working to this year
- Mid-October in-hands, imported item: finished and shipped before September 25. After that, plan on the second half of October.
- Anything imported that must land before the New Year shutdown: artwork approved by December 18, 2026. Rush air may stretch to the first week of January, but only if the factory says yes, and they say yes less often every day after Christmas.
- February and early March events: stocked or Canadian-made product, or an import ordered by mid-December and held here for you.
- First new imports after the holiday: by air, around the middle of March. By sea, late April.
If a spring program is already on your calendar, the most relaxed way to run it is to produce it before the break and let us hold the cartons. Storage is cheap; a missed launch is not.
A note for next year
Chinese New Year follows the lunar calendar and lands somewhere different every year. In 2028 it falls on January 26, which drags the shutdown back into mid-January. Programs that squeaked through in 2027 will need to order in November the year after. We post these dates every fall, and our customer service team is around Monday to Friday, 9 to 7 Eastern, to lay any order you are unsure about against the calendar with you.
Products mentioned in this article
Frequently asked questions
Which Delite products are not affected by Chinese holidays?
Anything stocked in our Markham, Ontario warehouse or made in Canada. Stocked items show a live inventory count on the product page and are decorated in-house, so they ship on our schedule. Canadian-made items such as black walnut boards, maple syrup and zero-waste soaps never touch the overseas calendar at all.
How long do factories close for Chinese New Year 2027?
Chinese New Year is February 6, 2027. Our suppliers close about ten days before and reopen about eight days after, so plan on January 27 to February 14, 2027, and expect them to run below full capacity until late February or early March while workers return.
What is the last day to order an imported item before the New Year break?
Have artwork approved by December 18, 2026 for standard production and air freight. Rush orders may be accepted into the first week of January, but only if the factory confirms it has capacity, so ask us before committing a date to your client.
Will the October Golden Week delay my order?
If the order is in production on October 1, yes. Factories close for seven to ten days and nothing ships from October 1 to about October 8, so plan on roughly two extra weeks. To have an imported item in hand by mid-October it needs to ship before September 25.
Can Delite produce an order early and hold it for me?
Yes. If you know a spring program is coming, we can produce it before the New Year shutdown and store the cartons in Markham until you need them shipped. It is the calmest way to run a February or March delivery on an imported product.
Context: State Council of the People's Republic of China, public holiday arrangements for 2026: https://www.gov.cn/zhengce/ · Hong Kong Observatory, Gregorian-Lunar calendar conversion (Chinese New Year 2027 = 6 February 2027; 2028 = 26 January 2028): https://www.hko.gov.hk/en/gts/time/conversion.htm